Mid-sized airports across the United States are managing significant infrastructure transformations throughout 2026 to address rapid traffic growth. According to Simple Flying Aviation Discovery, these regional facilities often face capacity limitations, where the number of available gates restricts airline service expansion. Fragmented terminal layouts frequently force passengers to choose specific security checkpoints before knowing which gate their flight will use. To rectify these constraints, airports are implementing projects that either add new gates, consolidate security into centralized checkpoints, or combine both strategies. Source
Modernization Programs at Regional Airports
Eppley Airfield (OMA) in Omaha represents the most advanced project on this list. In November 2026, the airport introduced four new gates, designated A1, A1A, A1B, and A2, as part of the $950 million Build OMA Terminal Modernization Program. Approved by the Omaha Airport Authority, the program will expand the facility from 375,000 square feet to 646,000 square feet. This project includes the addition of two international gates and a customs hall. Holder Construction, managing the project, broke ground in February 2024. Source
Delta Air Lines transitioned to the new gate space at Omaha in November 2026, replacing its previous south concourse area. Passengers currently continue to utilize existing security checkpoints within the south terminal, an arrangement scheduled to change with future construction phases. Once the modernization is complete, a unified concourse will link previously separated terminal areas, and all departing passengers will be directed to a centralized TSA checkpoint housed within a new pavilion that also features retail and dining options. Source
Omaha's project timeline remains active. The central pavilion and additional concourse sections are scheduled to open in early 2027, followed by the activation of new baggage and ticketing systems in mid-2027. According to reporting by WOWT, the full program is tracking on time and on budget for completion in 2028. FAA data indicates that Eppley enplaned 2,565,135 passengers in 2025. Despite a slight annual dip, the airport recorded a monthly peak of 530,157 passengers in June 2026. Source
Spokane International Airport (GEG) is executing its Terminal Renovation and Expansion (TREX) program. While classified as a small hub by the FAA based on 2,106,307 enplanements in 2025, it operates at a medium-hub scale. The $150 million Concourse C expansion reached its full completion on May 26, 2026, incorporating three new passenger boarding bridges to replace ground boarding at gates C1 through C3. This finished phase prepares the airport for the next, larger portion of the TREX program. Source
The upcoming Central Hall will consolidate security for all airlines into a single checkpoint and provide a post-security connection for concourses A, B, and C. Utility relocation to prepare the front curb site for this construction began in May 2026. The project has seen significant scope adjustments; a 2023 filing estimated the Central Hall at 145,000 square feet for $152 million, while current reports from the Journal of Business place the structure at 255,000 square feet with an estimated cost of $335 million. Source
Large-Scale Terminal Replacement and Growth
John Glenn Columbus International Airport (CMH) is currently managing the largest project of this group, the CMH Next program. This $2 billion initiative involves a complete replacement of the existing 1958 terminal. According to the Columbus Regional Airport Authority, the airport enplaned 4,396,625 passengers in 2025. The new terminal will feature 36 gates and a central marketplace with one unified security checkpoint, replacing the three checkpoints presently in operation. Source
Construction of the new facility at Columbus began in December 2024, starting with an elevated roadway. Structural progress is now in the vertical phase, following the installation of the first steel beam on August 8, 2025. The authority anticipates project completion in January 2029, a timeframe selected to coincide with the airport's centenary. The 1-million-square-foot facility is designed by Gensler and will increase waiting areas by 40% to 60%, with two gates dedicated to international service. Source
Richmond International Airport (RIC) has been reclassified as a medium hub after enplaning 2,481,863 passengers in 2025. The Capital Region Airport Commission is pursuing a $253.1 million Consolidated Security Screening Checkpoint project to replace the current bifurcated screening zones. The project includes 103,000 square feet of new construction and the renovation of 84,000 square feet of existing terminal space. The finalized design will support 10 screening lanes with the capacity for future expansion to 14. Source
Richmond's 2026 milestones focused on funding and design approval. In May 2026, the FAA provided a $5.8 million grant to support the checkpoint project. On October 27, 2026, the commission formally approved design contracts for the team led by the architecture firm Gresham Smith. Airport management intends to execute the construction in phases to minimize disruptions to passengers, though the exact opening date for the completed checkpoint remains undetermined at this stage of the development. Source
Boise Airport (BOI) is focusing exclusively on gate expansion rather than security consolidation. Following an 81% increase in passenger traffic over the last decade and 2,579,647 enplanements in 2025, the city council approved the Concourse A and Terminal Improvements project in August 2025. This $700 million contract with Hensel Phelps covers the addition of up to 10 new gates, an expanded baggage handling system, and a new central utility plant, with work scheduled through 2029. Source
The following table provides a summary of the infrastructure objectives and project timelines as identified in the 2026 reports for these five mid-sized US airports: Source
| Airport | Primary Infrastructure Goal | Expected Completion |
|---|---|---|
| Eppley (OMA) | Terminal Expansion and Gates | 2028 |
| Spokane (GEG) | Central Hall and Security Consolidation | 2030 |
| Columbus (CMH) | Terminal Replacement | 2029 |
| Richmond (RIC) | Consolidated Security Checkpoint | Not Stated |
| Boise (BOI) | Concourse A and Gate Expansion | 2029 |