Navigating Airport Construction and Road Changes
Spokane International Airport (GEG) is currently undergoing the second phase of its Terminal Renovation and Expansion (TREX) program. As part of this effort, a significant portion of the main terminal curbside was closed to vehicles and pedestrians on October 21, 2026. This closure is necessary to facilitate the relocation of essential water, sewer, and gas utilities. The work requires that all vehicle traffic be routed along a newly constructed two-lane bypass road, while pedestrians are directed to use designated skybridges. Source
To accommodate the construction, the airport has reduced inbound lanes from three to two. These traffic modifications and the associated utility relocation efforts are expected to persist until early 2027, with the broader curb and pedestrian bypass arrangement planned to remain in place through 2030. Airport officials have advised that these infrastructure adjustments are required to support the airport's expansion, which aims to meet projected passenger growth reaching over 6.2 million annual travelers by 2030. Source
Phase 2 of the TREX program, titled the Central Hall Project, focuses on creating a 255,000-square-foot facility at the center of the airport. This project aims to consolidate security screening, integrate baggage claim areas, and improve overall access to concessions. Demolition of a 149,000-square-foot area, which spans from the Concourse C parking garage to the skybridges for Concourses A and B, commenced in April 2026 to make space for this centralized facility. Source
In addition to road changes, the airport has eliminated its paid hourly parking lot. For visits lasting less than two hours, the airport currently recommends that motorists utilize the new Short-Term Parking Lot situated on the first floor of the parking garage. While drop-off remains available at specific sections of the terminal curb, the airport is encouraging loved ones to use the free cell phone lot until passengers have collected their luggage and are ready to be picked up. Source
Starting in February 2027, the existing Concourse C baggage claim will be decommissioned and eventually demolished. Passengers arriving on Alaska Airlines, Allegiant Air, and American Airlines will be directed to an interim baggage claim facility located in the Concourse C Plaza. This temporary arrangement is slated to remain operational through 2030. A shuttle bus service, running every 15 minutes, will be updated to include a stop between the temporary baggage claim area and the Ground Transportation Center. Source
Following February 2027, the existing hallway that currently connects the main terminal and the Concourse C ticketing area is also scheduled for demolition. In its place, the airport plans to utilize a temporary pedestrian pathway for traveler access. This pedestrian route is anticipated to be in use for the duration of the construction, potentially until 2030. Other airlines, including Delta Air Lines, Southwest Airlines, United Airlines, and Sun Country Airlines, will maintain their current baggage claim arrangements. Source
The TREX program is a long-term development initiative for the Inland Northwest. Phase 1, which involved the Concourse C Expansion, was successfully completed in June 2026. This initial phase added 144,000 square feet to the existing terminal, providing three new gates, six new ticket counters, and various amenities such as an Interfaith Prayer and Meditation Room and an Alaska Airlines Lounge. This foundational work was necessary to allow for the subsequent phases of the airport's modernization. Source
Project Scope and Financial Context
Financing for the TREX program currently supports Phase 1 and Phase 2, with costs reported at $150 million and $335 million, respectively. Any potential future phases, such as the modernization of Concourses A and B, remain dependent on securing additional funding. The Central Hall, once completed, will feature a consolidated TSA security checkpoint for all airlines and provide expanded connections between all three main concourses. Source
Spokane International Airport serves as a regional hub for the Inland Northwest. In 2025, the airport handled approximately 4.4 million passengers. While the airport has shown recovery and growth post-pandemic, it remains classified as a small hub by the FAA. It does not operate scheduled international passenger flights, although it maintains a Customs and Border Protection (CBP) port-of-entry office specifically for general aviation, charter flights, diversions, and cargo operations. Source
For travelers planning trips, the ongoing construction requires careful attention to signage and airport alerts. The phased approach taken by the airport management means that while facilities remain open, the ground-side flow is in a compromised state. Passengers are advised to allow extra time for parking and navigating the modified arrival and departure areas, as terminal access continues to be influenced by the ongoing utility and roadwork projects scheduled to run through 2030. Source
Key construction milestones and project timelines at Spokane International Airport are summarized in the table below to assist passengers in planning their travel throughout the multi-year construction period. Source
| Construction Initiative | Status / Date | Impact |
|---|---|---|
| Phase 1 Concourse C | Completed June 2026 | Added 144k sq ft, new gates, lounge |
| Utility Relocation | Ongoing until Early 2027 | Curb/pedestrian road bypass |
| Concourse C Baggage Claim | Decommissioned Feb 2027 | Transition to interim plaza facility |
| Central Hall / Phase 2 | Ongoing through 2030 | Consolidated TSA and baggage claim |